TAARIFA YA MATENGENEZO YA BARABARA WILAYANI HAI KWA MWAKA 2014/2015

Posted by Arusha by day and by night On 06:19 No comments



ACTION PLAN FOR MAINTENANCE OF DISTRICT ROADS BY ROAD FUND FINANCE YEAR 2014/2015
PACKAGING OF WORKS

SN
Road Name
Type of Maintenance
Length (Km)
Approved Budget (Tshs)
Implementation Period
1
Construction of Mnepo bridge
Bridge Construction
1No.
357,000,000
July-September

Total Package No.1

0
357,000,000

2
Shirinjoro-Lyamungo Sinde
Lyamungo Sinde-Mfoni
Shirinjoro-Lyamungo Sinde
Lyamungo Sinde-Kyalia
Elitira Mengi-Kyalia
Shirinjoro-Lyamungo Sinde
RM
RM
SI
RM
RM
PM
12
3
2
4
2
2
14,400,000
3,600,000
10,000,000
4,800,000
32,000,000
32,000,000


July-September

Total Package No.2

25
96,800,000

3
Kwasadala – Longoi
Bomang’ombe – Kikavuchini
Kwasadala – Longoi
Bomang’ombe - Kikavuchini
RM
RM
SI
PM
12.5
12
2
3
15,000,000
14,400,000
10,000,000
48,000,000

July-Septemba

 Total Package No.3

29.5
87,400,000

4
Sonu – Saawe
Kwasadala – Uswaa
Kwasadala –Uswaa
Sonu – Saawe
Lambo – Makoa
Bwani - Kyeeri
RM
RM
PM
PM
RM
RM
4
5.6
1
4
5
4
4,800,000
6,720,000
16,000,000
64,000,000
6,000,000
4,800,000


October-December

Total Package No.4

23.6
102,320,000

5
Kyuu – Lukani
Lukani – Mashua
Kwa Frank – Kyuu
Mbweera – Ufisi
Lukani – Mashua
Marukeni – Kyuu
Marukeni - Kyuu
RM
PM
RM
SI
SI
SI
RM
4
2.79
4
1.4
2
2
7
4,800,000
44,640,000
4,800,000
7,000,000
10,000,000
10,000,000
8,400,000


October- December

Total Package No.5

23.19
89,640,000

6
Marukeni - Kyuu
PM
5
80,000,000
January-March

Total Package No.6

5
80,000,000

7
Hai Town Roads
KIA – Mtakuja
Hai Town Roads
Construction of 1No.Vented Drift
PM
RM
PM
Construction
10
7.3
2
1No.
12,000,000
8,760,000
32,000,000
20,000,000

January-March

Total Package No.7

19.3
72,760,000

8
Shirinjoro – Mijongweni
Mferejini – Kimashuku – Kwatito
Shirinjoro – Mijongweni
Construction of 1No.Vented drift
1No.Bridege Repair-Weruweru
RM
RM
SI
Construction
Repair
5.17
7
0.83
1No.
1No.
6.204,000
8,400,000
4,150,000
20,000,000
10,000,000


April - June

Total Package No.8

13
48,754,000

9
Culvert Installation(No. 1 – No. 8)


52,270,000
July’13 – June’14
10
Supervision and Vehicle Maintenance(No.1 – No.8)


39,490,000
July’13 – June’14

GRAND TOTAL

138.59
1,026,434,000


Abbreviations
RM – Routine Maintenance
SI -    Spots Improvement
PM – Periodic Maintenance